A crane does not warn you before it tips. On Indian highway, metro, and EPC sites, lifting operations — cranes, hydras, tower cranes, slings and shackles — are responsible for some of the most severe accidents in the industry. The Samruddhi Expressway crane collapse in August 2023 killed 20 workers. Almost every investigation after a lifting accident finds the same thing: no lift plan, wrong SWL, uninspected slings. A lifting plan and lift inspection checklist does not slow the job down. It is what makes the job possible — safely, legally, and without a crisis call to the site manager at 2 am. This page gives you a complete, ready-to-use lifting plan and lift inspection checklist for Indian EPC, highway, mining, and infrastructure sites. Start free with HVI to run every critical lift digitally.

Plan · Inspect · Approve · Execute

Lifting Plan & Lift Inspection Checklist for Indian Sites

A complete lifting plan format and rigging inspection checklist for cranes, hydras, and lifting tackles on Indian EPC, highway, and mining sites. Covers SWL, slings, banksman, exclusion zone, and critical lift approval.

Critical Lift In Progress
LIFT-2026/041 · 250T Crawler
Load Weight48 MT
SWL Capacity250 MT @ 12m
Load %19.2% of SWL ✓
Exclusion Zone15 m radius
Approval Chain
Rigging Supervisor · P. Rao
Safety Officer · K. Sharma
Site In-Charge · V. Naik
Critical lift card: 250T crawler crane, load 48 MT at 19.2% of SWL, 15m exclusion zone, 3 of 3 approvals received
20
Workers Killed

Samruddhi Expressway crane collapse, Maharashtra, August 2023 — no pre-lift plan in place

NDRF incident report, India
90%
Human Error

Of all crane accidents are caused by human error — not equipment failure

Crane Inspection & Certification Bureau
75%
SWL Rule

Standard Indian EPC practice: never load a crane beyond 75% of rated SWL during a lift

EPC site SOPs, India
Mandatory
Legal Requirement

Lift plans required under Factories Act 1948, BOCW Rules, and DGMS mine safety regulations

Indian regulatory framework

When Is a Formal Lifting Plan Required on Indian Sites?

Not every crane lift needs a full critical lift plan. But if any one of these conditions is present, a formal plan is non-negotiable — legally and practically.

CRITICAL LIFT

Load > 75% of Crane SWL

Any lift where the load weight — including rigging, spreader beam, and attachments — exceeds 75% of the crane's rated capacity at the working radius.

CRITICAL LIFT

Lift Over Occupied Areas

Any lift where the load path passes over workers, moving vehicles, occupied structures, or live highway lanes.

CRITICAL LIFT

Tandem / Multi-Crane Lift

Any lift requiring two or more cranes to share the load simultaneously. Load distribution calculation is mandatory.

HIGH RISK

Within 6 m of Power Lines

Boom tip or load path coming within 6 metres of any energised overhead line. Clearance certificate and spotters mandatory.

HIGH RISK

Soft Ground / Unknown Bearing

Site where outrigger pad ground bearing capacity has not been confirmed. Mat or cribbing calculation required before setup.

STANDARD

Any Routine Crane / Hydra Lift

All crane and hydra lifts on Indian EPC, highway, and mining sites require at minimum a standard lift permit with SWL confirmation and rigging check.

HVI's lift plan module auto-classifies every lift as Critical, High Risk, or Standard the moment the load weight and crane data are entered. Book a 30-minute demo to see the classification live.

Sample Lifting Plan Format — Critical Lift

This is the standard lifting plan format used on Indian EPC, bridge, and infrastructure sites. Every section must be completed before the crane hook is attached to the load.

Critical Lift Plan
LIFT-2026/041
· Package NH-58
Crane Details
TypeCrawler Crane — 250T
Boom Length42 m
Working Radius12 m
SWL at Radius250 MT
Test CertificateValid — Mar 2027
Load Details
Item Being LiftedPrecast Box Girder
Gross Load Weight48 MT
Rigging Weight1.2 MT
Total Hook Load49.2 MT
% of SWL19.7% ✓
Site Setup
Ground ConditionSteel mats + cribbing
Exclusion Zone15 m radius barricaded
BanksmanR. Verma · Certified
Power LinesNone within 50 m
Wind Speed LimitMax 28 km/h
Rigging Configuration
Sling TypeWire rope, 4-leg, 32 mm
Sling SWL16 MT each leg
Shackle Rating25T bow shackle × 4
Spreader Beam8 m, SWL 60T certified
Tag Lines2 × 20 m nylon
Critical lift plan showing 250T crawler crane at 12m radius, 48MT precast girder at 19.7% of SWL, 15m exclusion zone, 4-leg wire rope rigging with certified spreader beam

Get the HVI digital lift plan free — fill on mobile, sign off in the app, close with photo proof.

Lift Inspection Checklist — Pre-Lift, During & Post-Lift

A lift inspection is not a single event. It has three distinct phases. Every phase must be signed off before moving to the next.

Phase 1

Pre-Lift Inspection

Before hook touches load
  • Crane test certificate valid and on site
  • Operator licence verified and current
  • Load weight confirmed — scale ticket or engineer calculation
  • SWL check done: load ≤ 75% of crane capacity at working radius
  • All slings inspected — no broken wires, kinking, or tag damage
  • Shackles inspected — pin straight, correct rating, cotter pin fitted
  • Spreader beam / lifting beam certified, SWL label visible
  • Ground bearing capacity confirmed, outrigger pads / mats in place
  • Exclusion zone barricaded and signed
  • Banksman / signaller assigned and positioned
  • Overhead power line clearance confirmed ≥ 6 m
  • Pre-lift toolbox talk conducted, all crew briefed
Phase 2

During-Lift Checks

While load is suspended
  • Test lift: raise 300 mm, hold 5 min, check balance and brake
  • No personnel under or within swing radius of suspended load
  • Banksman maintaining visual contact with operator at all times
  • Tag lines in use to control load swing
  • Wind speed within permitted limit (typically ≤ 28 km/h)
  • No sudden movements, jerking, or side-loading
  • All non-essential personnel outside exclusion zone
  • Load never left suspended unattended
Phase 3

Post-Lift Closure

After load is set down
  • Load secured and dunnage / support confirmed stable
  • All lifting tackles removed, inspected, and returned to store
  • Damaged slings / shackles tagged out of service immediately
  • Exclusion zone barricades removed or maintained as required
  • Lift record completed with photo proof of set-down
  • Supervisor sign-off on lift closure

Sling & Rigging Inspection — Discard Criteria

A sling that should have been removed two months ago is not a cost saving. It is a lawsuit and a fatality waiting to happen. These are the discard criteria that every rigging supervisor on an Indian site must know.

Rigging Item Inspect For Discard If
Wire Rope Sling Broken wires, kinking, birdcaging, corrosion, end ferrule ≥ 6 broken wires in one rope lay, or any kink / birdcage
Synthetic Web Sling Cuts, abrasion, UV discolouration, chemical damage, label legibility Any cut or burn, label missing, red core threads exposed
Chain Sling Chain link wear at crown, gouges, nicks, weld integrity Crown wear > 10% of original diameter
Shackle Body deformation, pin straightness, cotter pin, SWL marking Any bend, crack, or pin that will not fully seat
Hook Throat opening, twist, safety latch spring tension Throat opening > 15% of original, or latch not snapping
Spreader Beam Structural weld condition, end fittings, certification tag date Any crack in weld, end fitting deformation, or expired cert
Discard criteria for six types of lifting rigging: wire rope slings, synthetic web slings, chain slings, shackles, hooks, and spreader beams

HVI's rigging register gives every sling and shackle its own digital record — photo, cert date, inspection history, and auto-alert when it is due for re-inspection. Book a HVI demo to see a live rigging register on real fleet data.

Expert View from the Field

We were doing 6 to 8 lifts a day on our viaduct package. The lift plans were being done in a paper register at the site office. Half the time the register was not at the lift location. Slings were being used past discard criteria because nobody was tracking the inspection dates.

After we moved to HVI, every operator scans the sling tag before it goes on the hook. If the inspection date has lapsed, the app flags it and the lift cannot proceed. We caught three condemned slings in the first month that would have been used. That is not a near-miss story — that is three fatalities that did not happen.

Pradeep Rao, Rigging and Lifting Superintendent, GR Infraprojects, Rajasthan — NH-48 package, 14 cranes

Paper Lift Plan vs HVI Digital Lifting Plan

Paper Lift Plan
  • ×Lift plan register not at the lift location half the time
  • ×Sling inspection dates tracked manually — or not at all
  • ×SWL check done verbally — no written confirmation
  • ×Approvals collected face-to-face — can take hours
  • ×Post-lift closure forgotten, no photo evidence of set-down
  • ×Audit pack impossible to produce after an incident
HVI Digital Lift Plan
  • Lift plan raised on mobile at the lift location
  • Rigging register — every sling tagged, inspection auto-alerted
  • SWL check enforced: lift cannot proceed if load % exceeded
  • Multi-level digital approvals in minutes
  • Photo-verified closure with GPS and timestamp
  • Complete audit trail, one-click PDF for DGMS or client

For Indian EPC, highway, and metro sites running more than 5 lifts per day, digital lift plan management is the difference between a controlled operation and a criminal investigation. Sign up free with HVI and put every lift on one traceable platform.

Frequently Asked Questions

What makes a lift a "critical lift" on Indian construction sites?

A critical lift is any lifting operation that meets one or more of these conditions: the hook load exceeds 75% of the crane's rated SWL at the working radius, the load path passes over occupied areas or live traffic, the lift requires two or more cranes simultaneously, the crane boom operates within 6 metres of energised power lines, or the ground bearing conditions are unconfirmed. For DGMS-regulated mining sites in India, any lift involving HEMM components exceeding 10 MT also qualifies as a critical lift requiring formal sign-off.

How often should slings and rigging tackle be inspected in India?

All slings and rigging tackle must receive a pre-use visual inspection by the rigger before every single lift. In addition, a thorough inspection by a competent person is required every 6 months for rigging used in regular service and every 3 months for rigging used in severe conditions such as chemical environments, heat exposure, or high-frequency lifting. Any rigging exposed to shock loading, overloading, or unusual stress must be taken out of service and formally inspected before reuse. Under the Factories Act 1948 and applicable state rules, a register of all lifting gear with inspection dates must be maintained on site.

Who can be a banksman on an Indian construction site?

A banksman, also called a signaller or dogman, must be a trained and competent person who has been formally designated for the role on that specific lift. Under Indian EPC site practice and the BOCW Rules, the banksman must have undergone rigging and slinging training, must have a clear and unobstructed line of sight to both the crane operator and the load at all times, and must be the only person giving signals to the crane operator during the lift. The banksman's name must appear on the lift plan. If the banksman loses sight of the load at any point, the lift must stop immediately.

What should the exclusion zone radius be for a crane lift?

The exclusion zone must cover the full swing radius of the boom plus an additional buffer for the load's horizontal dimension and a drop zone below the full lift path. As a practical starting point, Indian EPC site SOPs typically set the exclusion zone radius at the working radius plus 3 to 5 metres, with a minimum of 10 metres for any lift above 5 MT. For lifts over occupied roads or railways, the exclusion zone must be formally approved by the competent authority and may require temporary lane closures or possession of the track. The exclusion zone must be physically barricaded and signed, not just marked on paper.

Can HVI generate a lift audit report for DGMS or client submission?

Yes. HVI's lifting plan module generates a complete, timestamped PDF lift record for any completed lift. The document includes the crane details, load weight and SWL check, rigging configuration, exclusion zone confirmation, banksman details, multi-level approval signatures with timestamps, pre-lift checklist with photo evidence, and the post-lift closure sign-off. The document is GPS-stamped at the site location and can be exported immediately for submission to DGMS, NHAI, NHIDCL, client EHS teams, or insurance bodies after any incident or routine audit.

Zero unchecked lifts. Zero surprises.

Sign Every Critical Lift Digitally with HVI

HVI gives Indian sites a complete digital lifting system. Lift plan on mobile, SWL enforcement, rigging register with auto-alerts, multi-level approvals, photo-verified closure, and a one-click audit PDF. Built for cranes, hydras, and tower cranes on EPC, highway, and mining packages.

No credit card. No hardware. Live on your site in under 10 minutes.